Warehouse extension at Burton On Trent, Derbyshire

Industrial concrete floor slabs, Burton On Trent

Level Best floor slab preparation has been working on site for the past three weeks now installing the intricate steel fabric reinforcement detail on this part ground bearing, part suspended cast insitu concrete floor slab. Stainless steel joint construction is to be installed as from next week in advance of the concrete floor pours. The concrete floor installation team are then booked in until the 12th January to lay the concrete floors utilising both laser screeds at the same time.

Should you like to know more information on our concrete flooring systems, please feel free to contact us on 01405 819199.

Comments are closed.