Level Best floor slab preparation has been working on site for the past three weeks now installing the intricate steel fabric reinforcement detail on this part ground bearing, part suspended cast insitu concrete floor slab. Stainless steel joint construction is to be installed as from next week in advance of the concrete floor pours. The concrete floor installation team are then booked in until the 12th January to lay the concrete floors utilising both laser screeds at the same time.